Planning · Timeline

How long does a Twin Cities bathroom remodel take?

Key takeaways

  • Castle Building & Remodeling’s 2026 Twin Cities guide puts a complete gut bathroom remodel at about 10–13 weeks. Precision Tiling, an Oakdale firm that serves St. Paul and the east metro, says about 3 weeks of build time and 3 to 6 weeks from signed proposal to final walkthrough.
  • Tile is a big block of time: Castle says an average bathroom floor and shower take over 100 hours of tile labor, which is more than two and a half 40-hour weeks for one installer.
  • Minneapolis estimates 15 business days for the first plan review on a one- or two-family remodel, plus five business days for each resubmission. Rough-in work must pass inspection before walls are closed.
  • Our illustrative 5 × 8 ft hall-bath schedule runs about 13 weeks from first call to final inspection, with the bathroom out of service for about 6 of them.
  • A one-day acrylic overlay (Bath Fitter) or a few-day shower system (West Shore Home) is advertised as far faster than a tiled job, with no tile to set.

Next step

Work through every step from scope and budget to the final inspection and lien waivers, in order.

A complete gut bathroom remodel takes about 10–13 weeks, “depending on how custom it is,” according to Castle Building & Remodeling’s 2026 Twin Cities Remodeling Cost Guide. Precision Tiling, an Oakdale firm that serves St. Paul and the east metro, says a full bathroom remodel typically takes about 3 weeks of build time, and 3 to 6 weeks from signed proposal to final walkthrough. The two firms define their periods differently, and their pages don’t explain the gap, so read each figure against its own definition.

Think of two clocks. The first runs from your first call to the day demolition starts: design, quotes, permits and ordering. The second is the stretch when the bathroom is out of service. A good plan keeps the second clock short by finishing the first one completely.

How long does a bathroom remodel take, by type of job?

Job What’s done Published time
Acrylic overlay Acrylic liner and one-piece walls go over the existing tub and walls One day (Bath Fitter)
Walk-in shower system, tear-out Old tub or shower removed; new low-threshold base and wall surrounds “A few short days” (West Shore Home)
Tiled tub-to-shower conversion Wet area rebuilt in tile, same footprint Often under 3 weeks (Precision Tiling)
Full remodel, tile-focused firm Room rebuilt with tile, fixtures and vanity About 3 weeks of build; 3–6 weeks proposal to walkthrough (Precision Tiling)
Complete gut remodel, design-build firm Room to the studs, design and custom work About 10–13 weeks (Castle)

Source: company pages listed below and Castle Building & Remodeling, 2026 Twin Cities Remodeling Cost Guide, p. 21 (accessed October 2026). Firms count different phases, so treat these as ranges, not a contest.

Two things take time in a tiled remodel. Castle’s guide says an average bathroom floor and shower take “over 100 hours” of tile labor, or more than two and a half 40-hour weeks for one installer. And inspections add waiting, because rough-in plumbing and wiring must pass before walls are closed.

Finish-only work is faster. Minneapolis exempts floor tile, cabinets and countertops, and wallpaper and paint from permits, and in one- and two-family homes, swapping a toilet or sink faucet without altering the piping. A refresh inside those limits has no permit wait.

Bathroom remodel timeline: the phases in order

  1. Planning and design. Measure, set a budget with the cost calculator and decide the layout; keeping fixtures where they are avoids relocating drains and supply lines. Then choose everything. Kuechle Construction, a Plymouth-based remodeler, says tile, plumbing trim, vanity, shower glass and specialty finishes should be chosen “before the room is torn apart.”
  2. Quotes and contract. Get at least three written quotes for the same scope, each with a schedule and start date. Check licenses on the DLI lookup; “IR” numbers are registrations, not licenses. Our quote checklist lists what to compare.
  3. Permits. A full remodel often needs a building permit plus separate trade permits. Minneapolis requires a plumbing permit to replace or install sinks, showers and tubs. Its permit steps for remodeling one- and two-family homes estimate 15 business days for the initial plan review and five business days each time plans are resubmitted. In St. Paul, of 454 bathroom-remodel permits that list required trade permits, 99% list plumbing, 81% electrical and 57% ventilation (our analysis of St. Paul permit data, which ends June 30, 2025). See the permit guide.
  4. Ordering. Order everything during the permit wait so the two overlap. Before demolition, confirm the vanity, tub or shower base, valve, tile and fan are on site or in the remodeler’s warehouse. Get firm dates in writing for made-to-order items such as a custom vanity, specialty tile or glass.
  5. Demolition. Older Twin Cities homes add work: Castle’s guide budgets $0–$3,000 to demolish a mud-set tile floor or wainscot in a hall bath and $0–$3,000 to remove and reset a radiator. In a home built before 1978, ask for EPA firm certification before demolition that disturbs painted surfaces. Check EPA coverage and exceptions when planning the scope.
  6. Rough-in and inspections. New drain and supply lines, the shower valve, wiring and the fan duct go in. In Minneapolis, rough-in plumbing and mechanical inspections come before anything is covered and before fixtures other than bathtubs are set. Any framing inspection follows once the rough-ins pass, and new insulation and vapor barrier get their own inspection.
  7. Waterproofing and tile. Backer board, a waterproofing membrane, the shower pan, then tile and grout. Some cities inspect the pan: Blaine requires a shower-pan inspection for tiled showers, and site-built pans must hold water for 24 hours in a flood test witnessed by the plumbing inspector.
  8. Fixtures and finishes. Vanity and top, toilet, faucets, shower trim, lights, fan grille, paint, accessories and any glass.
  9. Final inspections. Minneapolis does the final plumbing and mechanical inspections after fixtures are set, then the final building inspection once all trade permits have passed.
  10. Punch list and final payment. Walk the room with the remodeler and list anything unfinished. Minnesota’s pre-lien notice (Minn. Stat. 514.011) tells owners they may withhold amounts due to subcontractors and suppliers until 120 days after completion unless they get lien waivers, so ask for waivers with the final invoice.

Local note: In Minneapolis, electrical permits and inspections are issued and scheduled by the State (DLI), separately from the city’s plumbing, mechanical and building inspections. St. Paul inspects electrical itself. Minneapolis puts calling for inspections on the person doing the work, so ask your remodeler who schedules them.

Sample bathroom remodel schedule for a 5 × 8 ft hall bath

The schedule assumes a 5 × 8 ft three-piece hall bath (the size Castle’s guide uses for its hall-bath budget) in an older house: fixtures stay in place, a new tub, tiled floor and surround, new vanity, toilet, fan and lights, one tile installer and a permit that needs plan review.

Week What happens Bathroom usable?
1–2 Measure, set budget, choose layout and every finish Yes
2–4 At least three site visits and written quotes; license check; sign contract with a schedule Yes
4–7 Permit applications and plan review; order everything; confirm delivery dates Yes
8 Protect floors and the path out; demolition and haul-out; repair framing or subfloor No
9 Plumbing, electrical and fan rough-in; set the tub; rough-in, framing and insulation inspections No
10 Backer board and waterproofing; start floor tile No
11 Floor and wall tile No
12 Finish wall tile; grout; paint No
13 Vanity, toilet, faucets, trim, lights and fan; final inspections; punch list By week’s end

Source: PermitPriced illustrative schedule built from Castle (over 100 hours of tile labor), City of Minneapolis (15 business days for initial plan review) and the inspection order in Minneapolis’s “When to Call for Inspections” (accessed October 2026).

That adds up to about 13 weeks from first call to final inspection, with the bathroom out of service for about 6. The tile alone takes one installer more than two and a half weeks. Precision Tiling, a tile-focused firm, says about 3 weeks of build time. A design-heavy project, a moved toilet or a custom glass enclosure can add design, ordering or build time; Castle’s 10–13 weeks for a complete gut varies with how custom the job is. If you need the room done by a date, such as a holiday or a home sale, count back about three months and add a cushion.

Living without your bathroom during the remodel

During a full remodel, expect to have no shower in that room from demolition until the fixtures are set, which is about 6 weeks in our sample. Castle’s guide says that in a one-bath house “there are ways to keep a working toilet through the project, but not the shower.” The same FAQ suggests considering adding a second bathroom instead.

Before you sign, ask:

  • Which days will the water to the whole house be shut off?
  • Can the toilet be reset at night during any phase?
  • How will dust be contained, and which path will crews use?
  • Where will materials and the dumpster go?

Then line up a backup shower (a gym, family or a neighbor) for those weeks.

Best time of year to remodel a bathroom in Minnesota

A bathroom is interior work, so it can be done in any season. Winter brings a few things to plan for.

Keep the room warm. Waterproofing and setting materials have temperature limits. For LATICRETE’s HYDRO BAN, the surface must stay within 45–90°F during installation and for the next 24 hours. The technical sheet gives a typical wait of 2 hours after final cure at 70°F and 50% relative humidity before a flood test. At 50–69°F it specifies 24 hours after final cure. Ask the installer which conditions and waiting time apply to your room. Other products differ. If the radiator comes off or the room sits on a cold exterior wall, ask how it will be heated while the work cures.

Plan for open exterior walls. If an outside wall is opened, Minneapolis inspects new insulation and vapor barrier once installed and sealed. Plan the fan duct route at the same time; see our exhaust fan guide.

Allow for inspection waits. Blaine asks for 3 to 4 business days to schedule an inspection, and more during the busy construction season. Other cities differ, but every inspection is a point where work can pause.

The best season is the one that lets you finish planning first: plan over the winter, and you can sign, permit and order before your preferred start date.

What delays a bathroom remodel, and how to avoid it

Delay Why it happens How to avoid it
Selections not final Tile, trim or glass chosen after demolition Sign off on every finish before the demo date
Late made-to-order items Vanity, specialty tile or glass arrives after it’s needed Confirm items are on site before demolition
Hidden conditions Old drains, rot, mud-set tile, radiators behind the walls Keep a contingency; get unit prices for repairs in the contract
Permit resubmittals Incomplete or corrected plans go back for review Submit complete plans; in Minneapolis each resubmission adds about five business days
Inspection waits or failures Work can’t be covered until it passes Put inspection days in the schedule; ask who calls for them
Mid-job changes A new layout or fixture restarts ordering Decide before demolition; put any change order in writing with its time impact

Source: Kuechle Construction; City of Minneapolis; City of Blaine; Castle Building & Remodeling (accessed October 2026).

Local note: In Minneapolis, 57% of owner-occupied homes were built in 1939 or earlier, and in St. Paul it’s 53% (Census ACS 2020–2024). Walls that old can hide plaster over lath, thick mud-set tile and original piping, so a schedule for an older house should include some slack after demolition.

Watch out: Don’t let anyone close up walls or start tile before the rough-in inspections pass. In Minneapolis, the rough-in comes before anything is covered or concealed. Covering failed or uninspected work means tearing it out again.

More in common bathroom remodel mistakes.

Next steps

Ask every remodeler for a written schedule that names the start date, inspection points and the days you’ll be without the bathroom, and use the bathroom remodel checklist to make every selection before demolition.

Keep planning

Work through every step from scope and budget to the final inspection and lien waivers, in order.

Frequently asked questions

How long does a full bathroom remodel take?

Castle Building & Remodeling’s 2026 Twin Cities guide says a complete gut remodel takes about 10–13 weeks, depending on how custom it is. Precision Tiling, an Oakdale firm that serves St. Paul and the east metro, says about 3 weeks of build time and 3 to 6 weeks from signed proposal to final walkthrough. Each figure follows the firm’s own definition, and neither page explains the gap.

How long does a tub to shower conversion take?

It depends on the method. Bath Fitter says its walls install over the existing wall in one day. West Shore Home says its walk-in shower installs take a few days. Precision Tiling says its tiled conversions often finish faster than its 3-week standard. Our tub-to-shower conversion guide and one-day bath vs. full remodel guide compare each method’s scope, time and published prices.

How long does it take to get a bathroom remodel permit in Minneapolis?

For remodels of one- and two-family homes, Minneapolis estimates 15 business days for the initial plan review and five business days each time plans are resubmitted. Plumbing permits are separate, and electrical permits in Minneapolis are issued by the State.

What is the best time of year to remodel a bathroom in Minnesota?

A bathroom is interior work, so any season works. In winter, ask how the room will be kept warm: LATICRETE’s HYDRO BAN waterproofing, for example, requires a surface temperature of 45–90°F during installation and for the next 24 hours. Flood-test timing also depends on temperature and humidity.

Can I use my bathroom during a remodel?

Mostly not. Castle’s guide says that in a one-bath house there are ways to keep a working toilet through the project, but not the shower, so plan where you will shower for several weeks.

Sources

  1. 2026 Twin Cities Remodeling Cost Guide (opens in a new tab) — Castle Building & Remodeling. Accessed . Bathroom FAQ, page 21: gut remodel duration, tile labor, keeping a toilet in a one-bath house. Line items pages 14–16.
  2. Precision Tiling MN home page: process and FAQ (opens in a new tab) — Precision Tiling. Accessed . About 3 weeks of build time; 3 to 6 weeks from signed proposal to final walkthrough.
  3. Bathroom Remodel Cost St. Paul MN: 2026 Price Bands (opens in a new tab) — Precision Tiling. Accessed . Tub-to-shower conversions often finish faster than the firm’s 3-week standard.
  4. Bath Fitter Pricing (opens in a new tab) — Bath Fitter. Accessed .
  5. Walk-In Shower Replacement (opens in a new tab) — West Shore Home. Accessed .
  6. Bathroom Remodel Cost in Minneapolis (2026) (opens in a new tab) — Kuechle Construction. Accessed . Selections to make before demolition; page updated April 25, 2026.
  7. Construction permit application process (opens in a new tab) — City of Minneapolis. Accessed . Steps for remodeling or building one- and two-family homes; page last updated June 30, 2026.
  8. When to Call for Inspections (opens in a new tab) — City of Minneapolis, Construction Code Services. Accessed . Last updated April 1, 2024.
  9. Work exempt from permit (opens in a new tab) — City of Minneapolis. Accessed .
  10. Plumbing permits (opens in a new tab) — City of Minneapolis. Accessed .
  11. Approved Building Permits (opens in a new tab) — City of Saint Paul. Accessed . PermitPriced analysis of bathroom-remodel permits and their listed trade permits; data ends June 30, 2025.
  12. Local Code Lookup (electrical inspection authority by city) (opens in a new tab) — Minnesota Department of Labor and Industry. Accessed . Electrical inspection authority: State for Minneapolis, local for St. Paul.
  13. Bathroom Project (opens in a new tab) — City of Blaine. Accessed .
  14. HYDRO BAN technical data sheet (opens in a new tab) — LATICRETE International. Accessed . Surface preparation and flood-test waiting times for this membrane.
  15. ACS 2020–2024 5-year, table B25036 (tenure by year structure built), Minneapolis and St. Paul (opens in a new tab) — Census Reporter (U.S. Census Bureau data). Accessed . Owner-occupied homes built 1939 or earlier: Minneapolis 52,663 of 91,980; St. Paul 35,080 of 66,204.
  16. Lead Renovation, Repair and Painting Program Rules (opens in a new tab) — U.S. Environmental Protection Agency. Accessed .
  17. License and Registration Lookup (opens in a new tab) — Minnesota Department of Labor and Industry. Accessed .
  18. Minnesota Statutes 514.011, Pre-lien notice (opens in a new tab) — Minnesota Office of the Revisor of Statutes. Accessed .

Our guides are written independently, and we don’t rank remodelers. How we research.